Expert Assessment of the Natural Gas Bus Acquisition Process (Aveiro - Portugal)
Comprehensive expert assessment of the acquisition process for natural gas buses.
.jpg)
Phases: Development and Contruction

Project Details
Projects developed in the Area of waste to Energy have always been received with great receptiveness for decades.
Since then, we have developed and monitored the construction of incineration solutions tailored to the needs of the area where the waste is produced and where this solution is effective and energy efficient. The examples presented are proof that even in cities it is possible to build these units with a minimum impact on the surroundings.

Main Data
-
1- Location: Spittelau, Austria, Capacity: Electric Production: 40 MW, Steam Production 100 ton/h @32bar,240oC, Year: 1989/2013
-
2 - Location: Lenzing, Upper Austria, Capacity: Electric Production: 16 MW, Steam Production 120 ton/h @80bar,500oC, Year: 1998
-
3- Location: Linz, Austria, Capacity: Electric Production: 12MW, Steam Production: 80 ton/h, Year: 2012
-
4- Location: Niklasdorf, Austria, Capacity: Electric Production: 7 MW, Steam Production: 46 ton/h @40bar,400oC, Year: 2003
Services
01
Feasibility studies
02
Technical concept, Basic and Detailed Engineering
03
Supervision of Project Stage and Erection Works
04
.png)